Change inspection workflow: Example

The sequence in which sub-inspections and the tests for each sub-inspection display in a running inspection reflects the order in which those items display in the Inspection Editor from top to bottom.

Example

(Fig. 1) In the inspection Tube inspection below, Traceability would be the first sub-inspection to display in a running inspection, followed by sub-inspections Tube welds, Tube checks, and Audit form. The tests for  sub-inspection, such as those contained in the Traceability sub-inspection selected below, would be performed in the order as they display on the editor from top to bottom: Traceability - Shift, followed by Traceability - Department, Traceability - Serial number, Traceability - Temperature, Date/Time, and DMS Standard, respectively.

See Fig. 2 below for an example of how the sub-inspection Traceability and its tests for the inspection Tube inspection might display on a PC in a running inspection.

Fig. 1

Fig. 2

Changing the order of sub-inspections and tests